- Sweep upon completion of second & third story floor joist, right after subfloor and prior to electrical, plumbing and heating.
- After completion of roof sheathing, sweep units for electrician.
- Sweep second & third floors prior to lastical concrete and lightweight concrete operations.
- After roofs are complete, clean interior and exterior, hauling all scrap lumber prior to lathing operation.
- After electricians, sweep unit for framing inspection.
- Clean yards of all debris after lathing is completed, prior to plastering.
- Sweep prior to insulation.
- Dig around foundations prior to plastering.
- When trim and finish carpenters are completed, sweep for prime painters.
- Sweep for enamel painters.
- Haul all construction debris after plastering is completed and scaffolding is removed.
- Wash interior window glass and frames, and clean aluminum tracts and channels. Wash tubs and shower stalls.
- After finish plumbing, electrical and hardware, sweep and haul away all boxes and debris.
- Clean yards for finish grader.
- Wash exterior window glass and frames and clean aluminum tracts and channels while scaffold is still standing
- After all trades are completely finished, prior to City, VA, FHA, or other governing bodies.
- Inspection, dust out all cabinet drawers, shelves, ledges, etc., and wipe with oil cloth where appropriate.
- Clean all plumbing fixtures in bathrooms (tubs, sinks, showers, shower doors, ceramic tile
Pullman-vanity tops, mirrors, etc).
- Clean all kitchen appliances (range, oven, dishwasher, etc.), all counter
and bar tops, sweep entire unit and wet mop all tile floors.
- Clean F.A.U. cold air return compartment, F.A.U. platform, fireplace hearth and firebox.
- Upon completion of all of the above, haul away any remaining debris.
- Basement parking garages to be swept out three times as scheduled by the superintendent.
- All plaster droppings shall be removed from corridors & decks by plaster contractor and put on ground ground level for pick up.
- All roofers waste shall be put on ground level for pick up.
ALL OF THE ABOVE ITEMS ARE FOR ONE (1) COMPLETION ONLY. UPON APPROVAL, ANY REQUESTED ITEMS REPEATED WILL BE FOR AN ADDITIONAL FEE.
*EXCLUSIONS:
Drywall, drywall mud boxes,
concrete, concrete forms, fencing materials, landscaping debris, carpet scraps,
asphalt, dirt, rocks, trees, brush, erosion control debris, concrete washout
pits, paint containers and combustible materials. Excessive paint or silicone on
windows will not be removed. |